Permanent Sheet Pile Highways Retaining Wall in Cambridgeshire
16047
portfolio_page-template-default,single,single-portfolio_page,postid-16047,bridge-core-2.9.6,qode-page-transition-enabled,ajax_fade,page_not_loaded,,hide_top_bar_on_mobile_header,qode-theme-ver-28.0,qode-theme-bridge,qode_header_in_grid,wpb-js-composer js-comp-ver-6.7.0,vc_responsive
 

March, Cambridgeshire

About This Project

Permanent Highways Retaining Wall with a vibratory leader rig

Fussey Piling was invited to tender for a sheet pile highway retaining wall project in Cambridgeshire.

However, these ArcelorMittal AZ sheet piles have been installed in July! on a site in March, Cambridgeshire.

The 100m run of 8m long AZ sheet piles have been driven in less than 4 days with our powerful Bauer RTG 16T telescopic leader rig supported by our Sennebogen 630 crane.

Upon completion of the sheet piling our sister company, Fussey Engineering limited, installed a pressed steel capping beam to finish of the wall.